VALUE: $350,000
START DATE: December 2017
STATUS: Complete

Niclin Group worked closely with project Superintendent Honeywill Consulting to identify and implement a number of value engineered solutions to reduce the time and financial cost to the school.

The refurbishment of the existing structure included eight new motorised louvres, MDF feature panels to all of the walls and ceilings and the refurbishment of the multi-purpose court.

Works commenced during the school holidays and were completed during the first term of 2018. Working in a live school setting poses many unique challenges, so the team worked hard to cause minimal disruption to the school community.